| Payment Terms | L/C,T/T |
| Foundation | Concrete or glass fused steel |
| Easy to clean | Smooth, glossy, inert, anti-adhesion |
| Size Of Panel | 2.4M * 1.2M |
| Packaging Details | PE poly-foam between each two steel plates ; wooden pallet and wooden |
| Delivery Time | 10-30 days after deposit received |
| Permeability | Gas / liquid impermeable |
| Steel plates thickness | 3mm to 12mm , depends on the tank structure |
| Supply Ability | 60 sets per month |
| Tank Material | Glass fused to steel |
| Model Number | W |
| Brand Name | CEC TANKS |
| Place of Origin | China |
| Certification | ISO 9001:2008, AWWA D103 , OSHA , BSCI |
View Detail Information
Explore similar products
Glass-Fused-to-Steel Tanks for Cow Dung Anaerobic Digesters: Maximizing Biogas
The First Glass-Lined Steel Tanks Manufacturer in China
Glass Fused to Steel Potable Water Storage Tanks with Aluminum Dome Roofs:
Expandable Glass Fused to Steel Tanks Made of ART 310 Steel Plate: Advanced
Product Specification
| Payment Terms | L/C,T/T | Foundation | Concrete or glass fused steel |
| Easy to clean | Smooth, glossy, inert, anti-adhesion | Size Of Panel | 2.4M * 1.2M |
| Packaging Details | PE poly-foam between each two steel plates ; wooden pallet and wooden | Delivery Time | 10-30 days after deposit received |
| Permeability | Gas / liquid impermeable | Steel plates thickness | 3mm to 12mm , depends on the tank structure |
| Supply Ability | 60 sets per month | Tank Material | Glass fused to steel |
| Model Number | W | Brand Name | CEC TANKS |
| Place of Origin | China | Certification | ISO 9001:2008, AWWA D103 , OSHA , BSCI |
| High Light | fire-protection water storage tanks ,glass fused steel water tanks ,data center water storage hydraulics | ||
The storage tank is one component of a data center fire-protection system, not the whole of it. To size and place the tank correctly you have to design the system: how much water the protection demands, for how long, how the pump moves it, and how the whole arrangement stays reliable. This article covers that system logic so the tank is specified in context.
Design the data center fire-protection water storage as part of the system: set the required reserve from the protected-demand times the duration (commonly two to four hours), feed it through an NFPA 20 fire pump, provide a clean suction header with the right minimum depth, and add redundancy and relief where the code or risk calls for it. The tank volume follows from the demand and duration, not from a round number.
The reserve equals the worst-case protected demand (sprinkler density times area, plus any hose/standpipe allowance) multiplied by the required duration. Data centers often carry two to four hours of on-site reserve. Any credited incoming water reduces the tank volume only where the design permits.
| Input | Drives | Note |
|---|---|---|
| Sprinkler demand | Flow rate | Density x area. |
| Duration | Hours of reserve | Often 2-4 hr. |
| Hose/standpipe | Extra flow | Per design. |
| Incoming water | Volume credit | If allowed. |
The tank stores the reserve; the NFPA 20 pump delivers it at the required pressure. The tank must provide a suction with adequate submergence and a free surface so the pump primes reliably. Coordinate the tank outlet elevation and the pump suction requirements during design, not at hook-up.
Critical sites often split the reserve across two tanks or add a backup pump, and every tank needs an overflow/relief path sized to the fill rate. The system design, not the tank alone, delivers the reliability a data center expects.
Real fire-water tanks show the volume range a design can land on: the UAE Dubai fire-water tank at 652 m3 (2025) and the USA Porsche speedway fire-water tanks (2016) are delivered examples that a system design would size against the site demand.
Center Enamel supplies the fire-water tank with the load, suction and overflow basis documented, coordinating with the NFPA 20 pump and the system designer so the storage integrates rather than conflicts.
Protected demand times required duration (often 2-4 hr), plus allowances, minus any credited incoming water.
It delivers the stored reserve at the required pressure; the tank only stores it, so the two must be coordinated.
The pump needs adequate submergence to prime reliably; the tank outlet elevation must meet the pump spec.
Many critical sites do, across two tanks or with a backup pump, for redundancy.
An overflow/relief path sized to the fill rate so the tank cannot be overpressured during filling.
Yes - UAE Dubai 652 m3 (2025) and USA Porsche speedway (2016) are delivered fire-water references.
Treat fire-protection water storage as a system problem. Size the reserve from demand and duration, integrate the NFPA 20 pump through a proper suction, and add redundancy and relief by risk - then the tank becomes the reliable anchor of a design that passes inspection and protects the site.
Suggested CTA: Share your protected demand, duration and pump specification and we will size and detail the fire-water storage tank to integrate with your NFPA 20 system.
Company Details
Business Type:
Manufacturer
Year Established:
1989
Employee Number:
500~600
Ecer Certification:
Verified Supplier
Shijiazhuang Zhengzhong Technology Co.,Ltd is a professional manufacturer dedicated to the design and fabrication of bolted storage tanks since 2008. Our products range includes Glass-Fused-to-Steel (GFS) tanks, fusion bonded epoxy tanks, stainless steel tanks, galvanized steel tanks a... Shijiazhuang Zhengzhong Technology Co.,Ltd is a professional manufacturer dedicated to the design and fabrication of bolted storage tanks since 2008. Our products range includes Glass-Fused-to-Steel (GFS) tanks, fusion bonded epoxy tanks, stainless steel tanks, galvanized steel tanks a...
Get in touch with us
Leave a Message, we will call you back quickly!