| Delivery Time | 10-30 days after deposit received |
| Permeability | Gas / liquid impermeable |
| Size Of Panel | 2.4M * 1.2M |
| Packaging Details | PE poly-foam between each two steel plates ; wooden pallet and wooden |
| Payment Terms | L/C,T/T |
| Foundation | Concrete or glass fused steel |
| Easy to clean | Smooth, glossy, inert, anti-adhesion |
| Steel plates thickness | 3mm to 12mm , depends on the tank structure |
| Supply Ability | 60 sets per month |
| Tank Material | Glass fused to steel |
| Model Number | W |
| Brand Name | CEC TANKS |
| Place of Origin | China |
| Certification | ISO 9001:2008, AWWA D103 , OSHA , BSCI |
View Detail Information
Explore similar products
Glass-Fused-to-Steel Tanks for Cow Dung Anaerobic Digesters: Maximizing Biogas
The First Glass-Lined Steel Tanks Manufacturer in China
Glass Fused to Steel Potable Water Storage Tanks with Aluminum Dome Roofs:
Expandable Glass Fused to Steel Tanks Made of ART 310 Steel Plate: Advanced
Product Specification
| Delivery Time | 10-30 days after deposit received | Permeability | Gas / liquid impermeable |
| Size Of Panel | 2.4M * 1.2M | Packaging Details | PE poly-foam between each two steel plates ; wooden pallet and wooden |
| Payment Terms | L/C,T/T | Foundation | Concrete or glass fused steel |
| Easy to clean | Smooth, glossy, inert, anti-adhesion | Steel plates thickness | 3mm to 12mm , depends on the tank structure |
| Supply Ability | 60 sets per month | Tank Material | Glass fused to steel |
| Model Number | W | Brand Name | CEC TANKS |
| Place of Origin | China | Certification | ISO 9001:2008, AWWA D103 , OSHA , BSCI |
| High Light | Glass fused steel tank installation ,Bolted panel erection sequence ,Data center tank schedule | ||
A tank that is perfectly designed still has to appear on site, on the critical path, without damaging the coated panels. Installation is where many projects slip. For a data center, the bolted-panel method is chosen as much for its schedule predictability as for its coating quality. A missed tank milestone can delay the entire commissioning sequence, so the installation plan deserves the same rigor as the engineering.
Data center tank installation follows a repeatable sequence: factory packing of coated panels, container load, site foundation and anchor check, panel erection tier by tier with 8.8-grade bolts and butyl sealant, crane and crew coordination, and QA including bolt torque and a holiday-test record review. Bolted erection completes in days with a small crew, protecting the commissioning date; the sequence repeats cleanly across a multi-tank campus program.
Coated panels are crated to survive ocean freight, with mill and coating certificates shipped alongside. On arrival the foundation is verified against the anchor-bolt plan before any panel is lifted. Getting this handoff right prevents the most common delay: a foundation that does not match the tank.
Crews erect the shell tier by tier, placing a continuous butyl sealant and tightening 8.8-grade bolts to spec, then fit the roof, nozzles and accessories. The key QA steps are joint cleanliness, torque verification and a review of the 1500 V holiday-test record from the factory. Documenting these steps during erection, rather than after, is what keeps the handover clean.
| Step | Action | QA |
|---|---|---|
| Foundation | Verify anchors | Tolerance check. |
| Shell | Tier-by-tier bolt-up | Torque verify. |
| Roof | Fit panels/access | Alignment. |
| QA | Record review | 1500 V test + torque. |
Bolted erection needs no on-site coating, no radiography and no weld weather windows, so a small crew and a crane can finish in days. The Thailand installation used a six-person crew in twelve days, illustrating the speed a data center critical path can rely on.
Multi-tank programs repeat the same sequence phased to foundation readiness. The Indonesia Cilincing potable tank (21,088 m3, 2024) and the Namibia program of six 11,230 m3 tanks (2022) show single and multi-tank bolted erection at scale.
Center Enamel supplies the panels, the bolt/sealant/torque specification and erection supervision, so the data center tank installation is a governed sequence rather than an ad-hoc site build.
Often days with a small crew and crane, because there is no on-site coating, radiography or weld weather window.
A foundation that does not match the anchor-bolt plan; verifying anchors before lifting prevents it.
Joint cleanliness, bolt torque verification and review of the factory 1500 V holiday-test record.
Yes - the same sequence repeats phased to foundation readiness, as with multi-tank programs.
Usually the local contractor; the tank supplier provides supervision and the specification.
No - panels arrive pre-coated, which is a major schedule advantage over welded tanks.
Data center tank installation is a governed, repeatable sequence, not a site gamble. Pack the coated panels well, verify the foundation, bolt tier by tier with the right sealant and torque, and review the holiday-test record - and the tank comes online in days, repeatable across the campus.
Suggested CTA: Send us your tank count, volumes and foundation dates and we will return a phased erection plan with the bolt, sealant and torque specification plus supervision.
Company Details
Business Type:
Manufacturer
Year Established:
1989
Employee Number:
500~600
Ecer Certification:
Verified Supplier
Shijiazhuang Zhengzhong Technology Co.,Ltd is a professional manufacturer dedicated to the design and fabrication of bolted storage tanks since 2008. Our products range includes Glass-Fused-to-Steel (GFS) tanks, fusion bonded epoxy tanks, stainless steel tanks, galvanized steel tanks a... Shijiazhuang Zhengzhong Technology Co.,Ltd is a professional manufacturer dedicated to the design and fabrication of bolted storage tanks since 2008. Our products range includes Glass-Fused-to-Steel (GFS) tanks, fusion bonded epoxy tanks, stainless steel tanks, galvanized steel tanks a...
Get in touch with us
Leave a Message, we will call you back quickly!